Project Name : Boddington Gold Mine

Project Description :

Boddington Gold Mine Crushing Circuit and Leach Absorption Plant Removal 

Contract: Dismantle and removal of all reusable components of the Crushing Circuit and Leach Absorption Plant. 

Duration: 3 months 

Dual crane lifts were used in this project in numerous areas of the decommissioning.  Demolish and disposal of the balance of the plant consisting of approximately 2,000 tonne in total which was then transported to our Processing yard in Dardanup for further processing while awaiting export.

Part of this project was not just demolition for scrap, but also to on sell many of the usable components such as the Fine Ore Bin, pumps, surge tanks and storage tanks.